Site of the first 44,000 volt hydroelectric plant in America. Built in 1897 by Luclen L. Nunn at an estimated cost of just $50,000, the plant harnessed the power of the Provo River to generate electricity and transmit power over a distance of 32 miles to mining operations in Mercur, Utah. This was almost three times the voltage of any existing line in the nation at that time, and was by far the longest. Although Nunn sold his interests to Utah Power and Light Company in 1913, his innovative ideas and successes helped shape the future of electrical power for all of us.

1898

2022

[bafg id=”113″]

1971

2022

[bafg id=”165″]

The pictures below are taken from standing on the side of the mountain looking down at the site. As you can see the building took up most of the space where the parking lot is today.